wagonwagonwagonwagonwagonwagonwagon

Winter Works

TRAINS HOME

MAPS

OPEN DAYS

SPECIAL EVENTS

2010 - 2011

 Work has been progressing on track renewals. The major activity has been on the curve immediately after the tunnel.

View towards tunnel wide New concrete bases have been cast for the track support piers. This view is looking back towards the tunnel.
View towards tunnel close A closer shot showing the concrete trusses that are being tried on curves instead of old railway sleepers.
Setting a level 1 190311 Setting a long distance level.
Setting a level 2 190311 Setting the level of individual trusses.
Concreting 190311 Concreting in between the trusses.
Painting the railings 190311 Painting the railings round the station.
Water Tower 190311 The water tower has received new cladding as part of the works from the generous grant received last year.
last few pieces of track to go in Last few pieces of track to go in
Cutting track to fit Cutting track to fit
Fixing track down Fixing track down
Making alignment adjustments Making alignment adjustments
Filling in around piers Filling in around piers
Repairing vandal's damage to gate Repairing vandal's damage to gate
Tea time Always time for a brew
   

2009 - 2010

Snow at Marley Jan 7th Snow stopped work on January 7th 2010
Snow at Marley Jan 7th Looking down the back straight that was rebuilt last year
Snow at Marley Jan 7th The station area that is being rebuilt this winter
station works 1 2010 By the beginning of February the footings were in along the platform
Station works 2  
Station works 2010  
Station works 2010 A week later and the steaming bay area had been reached
Station works 2010  
Station works 2010  
   
Station works 2010 Block work was added to form a firm base
Station works 2010  
Station works 2010  

 

2008 - 2009

 

 During the winter track renewal is taking place at Marley. On Wednesday and Saturday mornings work is taking place to renew 70 meters of track along the 'back straight'. The photographs below will tell the story when we remember to take them!

Track_foundations_001 Having dismantled the old track the next job was to dig a long trench
Track_foundations_002 Action shot of the new footings being laid on Saturday 31st January
Track_foundations_003 Nearly a third of the footings in place
Winter works 4 Saturday 14th February, reclaimed supports going on the slabs
Winter works 5 Next four footings going in
Winter works 6  
Winter works 7 Lining up the pillars
Winter works 8 A good morning's work
We are on the last leg 1 Filling the trench back in on the 4th of March
We are on the last leg 2 Good to see the younger ones helping
We are on the last leg 3 Keith tries his hand with the digger
We are on the last leg 4 More practice needed!
We are on the last leg 5  
We are on the last leg 6 Saturday 21st March and the new railway sleepers are on the pillars
We are on the last leg 7  
We are on the last leg 8 Just the track needed back on here
We are on the last leg 9 The last few plinths being made 
the final bolt goes in by our President 1 Saturday 4th April and the track is back together
the final bolt goes in by our President 2 Change of camera crew!
Long straight relaid winter 09 And this is how it looks as the grass is starting to grow back.
Bridge repainted over winter 09 Other work was done around the site as well. The bridge was cleaned of the rust and old paint and given a new coat of paint. The job was finished off with new handrails.





Home

Contact Trains

 

Webtrains by Mike Badger

 

This page was last updated on Thursday 31st March 2011 at 21:00.
If you have arrived at this page and it isn't in a frame, click here to re-enter the site via our index page.

Web Master