|
|
Winter Works
2010 - 2011
Work has been progressing on track renewals. The major activity has been on the curve immediately after the tunnel.
![]() |
New concrete bases have been cast for the track support piers. This view is looking back towards the tunnel. |
![]() |
A closer shot showing the concrete trusses that are being tried on curves instead of old railway sleepers. |
![]() |
Setting a long distance level. |
![]() |
Setting the level of individual trusses. |
![]() |
Concreting in between the trusses. |
![]() |
Painting the railings round the station. |
![]() |
The water tower has received new cladding as part of the works from the generous grant received last year. |
![]() |
Last few pieces of track to go in |
![]() |
Cutting track to fit |
![]() |
Fixing track down |
![]() |
Making alignment adjustments |
![]() |
Filling in around piers |
![]() |
Repairing vandal's damage to gate |
![]() |
Always time for a brew |
2009 - 2010
![]() |
Snow stopped work on January 7th 2010 |
![]() |
Looking down the back straight that was rebuilt last year |
![]() |
The station area that is being rebuilt this winter |
![]() |
By the beginning of February the footings were in along the platform |
![]() |
|
![]() |
|
![]() |
A week later and the steaming bay area had been reached |
![]() |
|
![]() |
|
![]() |
Block work was added to form a firm base |
![]() |
|
![]() |
2008 - 2009
During the winter track renewal is taking place at Marley. On Wednesday and Saturday mornings work is taking place to renew 70 meters of track along the 'back straight'. The photographs below will tell the story when we remember to take them!
![]() |
Having dismantled the old track the next job was to dig a long trench |
![]() |
Action shot of the new footings being laid on Saturday 31st January |
![]() |
Nearly a third of the footings in place |
![]() |
Saturday 14th February, reclaimed supports going on the slabs |
![]() |
Next four footings going in |
![]() |
|
![]() |
Lining up the pillars |
![]() |
A good morning's work |
![]() |
Filling the trench back in on the 4th of March |
![]() |
Good to see the younger ones helping |
![]() |
Keith tries his hand with the digger |
![]() |
More practice needed! |
![]() |
|
![]() |
Saturday 21st March and the new railway sleepers are on the pillars |
![]() |
|
![]() |
Just the track needed back on here |
![]() |
The last few plinths being made |
![]() |
Saturday 4th April and the track is back together |
![]() |
Change of camera crew! |
![]() |
And this is how it looks as the grass is starting to grow back. |
![]() |
Other work was done around the site as well. The bridge was cleaned of the rust and old paint and given a new coat of paint. The job was finished off with new handrails. |
Webtrains by Mike Badger
This
page was last updated on
Thursday 31st March 2011 at 21:00.
If you have arrived at this page and it isn't in a frame,
click
here to re-enter the site via our index page.